Highway 57 Project - Forecast for week of July 7, 2025
July 07, 2025
The crew is starting the gravity sewer line installation this week, working Northward from the Lutheran Church. Once the crew starts making progress, we should be able to predict the rate of pipe installation per day.
Also this week, the boring crew will be installing HDPE piping from the bore pit on the West side of Hwy 57 up the hill to near Lift Station #5 which is along side FS 1048 near the lagoons and Woodrat road.
We will continue to alert homes and businesses along the excavation path when work is imminent and will keep any disruptions a short as possible.